| From
Node |
To
Node |
Comment |
| A |
B |
A
"channel" link should be used to connect these two nodes
together. It is the approach to the spillway between nodes B and
C.
|
| B |
C |
This
spillway is actually the original entrance to the tunnel system.
A weir controls water levels in the upstream channel and then a
spillway drops approximately 4-5-feet onto a concrete apron. The
original headwall to former tunnel system was left in place
immediately downstream of the spillway because it supports a water
main located on top of it. Therefore, after water drops over the
spillway, it must pass through an arch opening (approx. 2 feet in
length) before moving into the sheet piled open channel system.
A
"drop structure" link should be used to connect node B to
node C. A drop structure in ICPR is a weir in series with a
pipe. In this case, the pipe would have an arch geometry with a
pipe length of only 2 feet. This would restrict the cross
sectional area beyond the spillway to the original tunnel opening
size. In essence, the opening acts similar to a very large
orifice.
|
| C |
D |
Vertical
sheet piles are used along this segment of channel forming a
rectangular cross section. There is cross bracing at the top to stabilize
the sheet piling.
A
"channel" link should be used to connect node C to D.
Either a trapezoidal cross section with zero side slopes could be used
or an irregular cross section. Manning's n could be adjusted to
account for the cross bracing.
|
| D |
E |
This
roadway crossing could be modeled as either a "bridge" link
or a "pipe" (culvert) link.
|
| E |
F |
A
"channel" link would be used to connect these two nodes,
similar to link C-D.
|
| F |
G |
This
roadway crossing could be modeled as either a "bridge" link
or a "pipe" (culvert) link.
|
| G |
H |
As
water exits from under the roadway, the channel rapidly flares out to
a wide section and then tapers down again as it approaches node G.
A
"channel" link should be used here with irregular cross
sections defined at each end of the link. ICPR allows
non-prismatic channel links and consequently can accurately account
for expansion and contraction losses. (Note: Many programs similar to
ICPR (e.g., SWMM) do not allow non-prismatic channel links between two
nodes.)
|
| H |
I |
There
is a grade break (approx. 2') at node H formed by gabions in the
bottom of the channel. Although another node (say, H') could be
placed immediately downstream of node H and the two connected together
with a weir, it's not necessary because of the way geometry and
inverts are specified for channel links in ICPR.
Instead,
node H is connected to node I with a channel link. The upstream
invert elevation of this channel link would be approx. 2' below the
downstream invert of link G-H and the drop would automatically be
included in the calculations.
|
| I |
J |
A
"channel" link would be used to connect these two nodes
together. This reach of the channel system is flatter than other
parts and is earthen-lined with selected wetland plantings.
|
| J |
K |
There
is a narrow pedestrian bridge crossing the channel between nodes J and
k that could influence the hydraulics for major storm events.
Additionally, there is a 2-foot (+/-) grade break directly below the
bridge.
Node
J could be connected to node K with either a "weir" link or
a "bridge" link. Either would work in this case
although the bridge might be a better choice for major storm events.
|
| K |
L |
A
"channel" link would be used to connect nodes K and L
together. This is a high energy area and the bottom of the
channel and a portion of the side slopes are lined with gabions and
riprap.
|
| L |
M |
A
"channel" link would be used to connect these two nodes
together. This reach of the channel system is flatter than other
parts and is earthen-lined with selected wetland plantings.
|
| M |
N |
There
is another grade break (approx. 2') at node M formed by gabions and
riprap in the bottom of the channel. This is similar to the
situation at node H and is handled the same way.
Node
M is connected to node N with a channel link. The upstream
invert elevation of this channel link would be approx. 2' below the
downstream invert of link L-M and the drop would automatically be
included in the calculations.
|
| N |
O |
This
is a roadway crossing with another grade break below the bridge
similar to link J-K. It can be modeled the same way, with either
a bridge link or a weir link. The bridge link is probably better
suited for major storm events.
|
| O |
P |
A
gabion lined rectangular channel section is located beyond the roadway
crossing N-O. A "channel" link should be used here and
an exit loss should be applied because the channel expands abruptly at
node P.
|
| P |
Q |
This
channel segment gradually tapers from a very wide cross section to a
narrower one at node Q. A "channel" link should be
used here. Contraction losses due to the narrowing cross section
are included in the computations.
|